飘窗板悬挑脚手架施工方案剪力撑:G8=0.4KN
安全网:G9=0.005KN/㎡×2×12.8=0.128KN
恒载:NG1=0.72G1+(G2+G3+G4+G5+G6+G7)×1/2
CBDA 25-2018-T标准下载=0.72×1.022+(0.144+1.11+0.921+1.11+1.29+1.9)×1/2=3.97KN
NG2=0.48G1+(G2+G3+G4+G5+G6+G7)×1/2+G8+G9
=0.48×1.022+(0.144+1.11+0.921+1.11+1.29+1.9)×1/2+0.4+0.128=4.25KN
施工活荷载:NQ1=1/2(1+0.2/1)2q
=0.72×5.4=3.89KN
NQ2=1/2(1-0.22/1)q
=0.48×5.4=2.59KN
总竖向荷载:N1=1.2NG1+1.4NQ1=1.2×3.97+1.4×3.89
N1=1.2NG2+1.4NQ2=1.2×4.25+1.4×2.59
2、∮48钢管斜撑的计算
按偏心受压,斜撑承受全部竖向荷载
L1=(3.052+0.442)1/2=3.08m
L2=(3.052+1.42)1/2=3.36m
为增加稳定性,增加二道支撑,共计算长度为
l01=kμl1/3=1.155×1.5×3.08/3=1.78m
l02=kμl2/3=1.155×1.5×3.36/3=1.95m
λ1=l01/i=1.78/1.58=112.7
λ1=l02/i=1.95/1.58=123.4
ε=e×A/w=6.5㎝×4.89㎝2/5.08㎝3=6.26
查得φ1=0.115φ2=0.111
由偏心产生的弯矩分别为
M1=e×N1’=e×N1/cosα3=65×10210/0.99=670353N·㎜
M2=e×N2’=e×N2/cosα4=65×8730/0.909=624257N·㎜
N1/φ1cosα3A1=10210/0.115×0.99×489=183.39N/㎜2
<f=205N/㎜2可以。
N1/φ2cosα4A2=8730/0.111×0.909×489=176.94N/㎜2
<f=205N/㎜2可以。
3、端部预埋∮22抗剪钢筋的验算:
τ1=N1’×sinα3/3.14×112=10210×(sin8.21/3.14×112)
=3.84N/㎜2<τ=125N/㎜2可以。
τ2=N2’×sinα4/3.14×112=8730×(sin24.66/3.14×112)
=9.58N/㎜2<τ=125N/㎜2可以。
ωk=0.7μ2μsω0=0.7×1.67×(1.3×0.5)×0.7=0.53KN/㎡
由风荷载产生的轴向力:
Nω=1.4ωkAω=1.4×0.53×3.2×3.6=8.55KN
N1=Nω+N0=13.55KN<2×8KN=16KN
连墙杆稳定性验算:λ=I/i=30/1.58=19
N1/φA=16×103/0.949×489=34.5N/㎜2<f=205N/㎜2可以。
5、小横杆、大横杆、立杆的计算:
(1)AB杆或小横杆的计算
查表:Mmax=0.398KN/m
Vmax=1.65㎜<L/150=1000/150=6.7㎜可以。
б=M/ω=0.398×106/5.08×103=78.35N/㎜2
<f=205N/㎜2可以。
б=M/ω=0.912×106/5.08×103=179.6N/㎜2
FA-23钢筋闪光对焊和水平钢筋窄间隙焊施工方案<f=205N/㎜2可以。
Vmax=kpL3/100EI=9.4㎜<L/150=1800/150=12㎜可以。
(3)外立杆的计算;由风荷载引起的弯矩
ωk=0.53KN/㎡la=1.8mh=1.5m
Mω=0.85×1.4Mωk=0.85×1.4×ωk×la×h2/10
=0.85×1.4×0.53×1.8×1.52/10=0.2554KN·m
λ=l0/i=kμh/i=1.155×1.5×150/1.58=164.5
N/φA+M/ω=1.2×4.39×102/(0.231×4.89×102)+0.2906×106/5.08×103
土地整理施工组织设计样本=103.8N/㎜2<f=205N/㎜2可以。