施工组织设计下载简介
内容预览随机截取了部分,仅供参考,下载文档齐全完整
某厂区室外中压电缆敷设施工组织设计方案2)每盘电缆上应标明电缆规格、型号、电压等级、长度及出厂日期。电缆盘应完好无损。
Eachcableshouldbemarkedonspecification,model,voltagelevel,lengthandmanufacturedate.Cabletrayshouldbeinagoodcondition.
3)电缆外观完好无损,铠装无锈蚀、无机械损伤,光泽明亮无皱折和扭曲现象。电缆外皮及绝缘展无老化及裂纹。
xx人民消防工程施工组织设计Thecableexteriorconditionisintact.Thearmorhasnorustandnomechanicaldamage.Itisshinyandbrightwithoutwrinklesanddistortions.Cablejacketandinsulationshownoagingandcracks.
4)电缆敷设前进行绝缘摇测或耐压试验。测量绝缘用兆欧表的额定电压,采用如下等级:Beforelayingcarryoutinsulationrollingtestorvoltagewithstandtest.Usemeggerratedvoltagetomeasureinsulation.Takethefollowinglevel:
10KV和35KV电缆:用2500V兆欧表。10KVand35KVCable:The2500Vmegger.
5)按设计和实际路径计算每根电缆的长度,合理安排每盘电缆,无电缆接头。Calculateeachcablelengthaccordingtodesignandactualpath.Arrangeeachcablereasonablywithoutcablejoints.
6)电缆保护套管已经预埋好,故只需要清理管内残渣,并作好管口保护。Cableprotectionsleevehasbeenembedded.Cleanpiperesidueandprotectnozzles.
7)其它附属材料:电缆标示桩、电缆标志牌、油漆、汽油、封铅、硬脂酸、白布带、橡皮包布、黑包布等均应符合要求。Othersubsidiarymaterial:cablemarkingpiles,cablesigns,paint,gasoline,sealedlead,stearicacid,whitebelt,rubbercloth,blackclothetc.shouldmeettherequirements.
4.3主要机具准备MainEquipmentPreparation
卷扬机、敷设电缆用支架及轴、电缆滚轮、转向导轮、吊链、滑轮、钢丝绳、大麻绳、千斤顶。Winches,bracketandshaftforcablelaying,cableroller,transferguidewheel,hangingchain,pulleys,wirerope,largehemprope,jacks.
4.4作业环境准备WorkEnvironmentPreparation
场地清理干净、道路畅通。Sitecleanuptheroadsunimpeded
放电缆用的设备安置完毕,且符合安全要求,电缆沿线照明照度满足施工要求。
Cablelayingequipmenthasplaced,andmeetssafetyrequirements.Cablelightingilluminationalongtheroutemeetstheconstructionrequirements.
五.敷设施工WorkofCablePulling
5.1电缆敷设施工工序WorkProcedure
机具布置→电缆展放→电缆敷设、固定Equipmentlayout→Layoffcable→laycableandfix
5.2机具布置LayoutofTools
5.2.1电缆的搬运及支架架设CableRemovalandCableTray
5.2.2卷扬机与滑轮的布置WinchandPulleyArrangement
电缆架与卷扬机布置见下图:Cablerackandwincharrangementseebelow:
1)电缆展放可用人力拉引或机械牵引。当采用机械牵引时,用机械的最大牵引强度宜满足下表的规定,其速度不宜超过15m/min,且应在牵引头或钢丝网套与牵引钢缆之间装设防捻器。Usemanualormechanicaltraction.Whenusingmechanicaltraction,themaximummechanicalstrengthshouldmeettherequirementsinTable,itsspeedshouldnotexceed15m/min,andshouldinstallfortifiedtwisterbetweentractionheadorsteelmeshsleeveandpullingsteelcable.
Cablemaximumtractionstrength(N/mm2)
电缆最大牵引强度(N/mm2)
牵引方式traction
牵引头tractionhead
钢丝网套steelmeshsleeve
铝芯aluminumcore
铝套aluminumsheath
塑料护套plasticsheath
允许牵引强度allowabletractionstrength
本次采用机械牵引,采用钢丝网套直接塑料护套方式,按表计算允许最大牵引强度:Themechanicaltractionusesaluminumandplasticsheath.Calculateallowablemaximumtractionstrength:
35KV电缆:300mm2的单芯电缆,其允许最大牵引强度:
35KVcable:300mm2singlecable,theallowablemaximumtractionstrength:
F1=7*300=2100N
10KV电缆:95mm2的三芯铠装电缆,铅套,其允许最大牵引强度:
F2=10*95*3=2850N
185mm2的三芯铠装电缆,铅套,其允许最大牵引强度:
F3=10*185*3=5550N
2)牵引力和侧压力计算:Tractionandlateralpressurecalculation:
侧压力计算公式为:Thecalculatingformulalateralpressure:P=T/R
式中:P为侧压力(N/m);T为牵引力(N);R为弯曲半径(m)
Where:Pforlateralpressure(N/m);Tfortraction(N);Rforthebendradius(m)
式中:μ为摩擦系数,在滚轮上牵引时取0.1~0.2;
Where:μisfrictioncoefficient,wheeltractionis0.1~0.2
W为电缆每米重量(kg/m);L为电缆长度(m)
Wiscablepermeterweight(kg/m);Liscablelength(m)
实际施工中,考虑实际情况,μ取0.12,R1取0.5m,R2取1.3m,R3取1.5m
Theactualconstructionshouldconsideractualcircumstances,μtakes0.12,R1takes0.5m,R2takes1.3m,R3takes1.5m
令T1=F1=2100N,则L1=2100/(9.8*0.12*4.17)=428m
T2=F2=2850N,则L2=2850/(9.8*0.12*4.04)=600m
T3=F3=5550N,则L3=5550/(9.8*0.12*6.44)=733m
P1=2100/0.5=4200N
P2=2850/1.3=2192N
P3=5550/1.5=3700N
所以,采用塑料护套直接拉动电缆时,35KV电缆每次允许拉428m电缆,其侧压力为4200N;10KV95mm2的电缆每次允许拉600m,其侧压力为2192N;10KV185mm2的电缆每次允许拉733m,其侧压力为3700N。Therefore,pullthecablewithplasticsheath.Eachtimetheallowablelengthof35KVcableis428manditslateralpressureis4200N;10KV95mm2cableis600mand2192Nand10KV185mm2cableis733mand3700N.
3)电缆展放时,电缆应从盘的上端引出,不应使电缆在地面摩擦拖拉。电缆上不得有铠装压扁、电缆绞拧、护层折裂等未消除的机械损伤。Pullcablefromtheupperplatetoavoidfrictionontheground.Armoredcablemaynotbecrushed.Donothavecabletwisted,retaininglayerfractureandothernoteliminatedmechanicaldamage.
5)每根电缆敷设好后,在电缆两端做好临时标示,以分清电缆回路及黄、绿、红三相。Maketemporarysignsatbothendsofcables.Identifycableloopandyellow,green,redphases.
5.4电缆敷设、固定CableLayingandFixing
2)电缆之间,电缆与其它管道、道路、建筑物等之间平行和交叉时的最小净距,应满足规范的要求。Theminimumparallelandcrossspacing betweencablesorbetweencablesandotherpipeline,roads,buildings,etc.shouldmeetthespecificationrequirements.
3)电缆与现有电缆交叉时,满足规范要求,保持足够间距。Crossoveringtheexistingcablestomeettheregulatoryrequirementsandmaintainadequatespacing.
5)冬季敷设电缆,温度达不到规范要求时,应将电缆提前加温。Inwinter,whenthetemperaturecannotmeetregulatoryrequirements,thecableshouldbeheatedinadvance.
六.覆砂盖砖SpreadSandandCoverBricks
1)电缆敷设完毕,应请建设单位、监理及质量监督部门作隐蔽工程验收,作好记录、签字。Askconstructionunit,supervisionandqualitysupervisiondepartmentsacceptconcealedproject,makerecordsanddothesignature.
2)电缆上面与电缆下面一样,覆盖10cm砂土或软土,然后用砖或电缆盖板将电缆盖好,覆盖宽度应超过电缆两侧5cm。Spread10cmsandorsoftsoilaboveorbelowcableandcoverwithbricksorboardswithwidthmorethan5cmofbothsides.
七.回填土BackfillEarth
1)直埋电缆回填土前,应经隐蔽工程验收合格。PriortoBuriedcablebackfillshallbeaccepted.
八.埋标桩BuryingStake
九.挂标志牌Hangingsigns
1)标志牌规格应一致,并有防腐性能,挂装应牢固。Thesignsshallbethesamesize,haveantisepticproperties,andmountedhangingshallbefirmly.
2)标志牌上应注明电缆编号、规格、型号及电压等级。Thesignsshouldindicatecablenumbers,specifications,modelsandvoltagelevel.
3)直埋电缆进出建筑物及电缆终端头应挂标志牌。Buriedcableaccesstobuildingsandcableterminationheadsshouldhangsigns.
4) 电缆标志牌同时应遵循业主标准。Cablesignsfollowownerstandard.
十.质量控制QualityControl
10.1主控项目MasterItems
检验方法:检查试验记录。TestMethod:Checktestrecords.
电缆敷设必须符合以下规定:电缆严禁有绞拧、铠装压扁、护层断裂和表面严重划伤等缺损,直埋敷设时,严禁在管道上面或下面平行敷设。Thecablelayingmustmeetthefollowingrequirements:Strictlyprohibittwist,armoredsquash,sheathfractureandseverelacerationsandothersurfacedefects.Forbidparallelpipelinelaying.
检验方法:观察检查和检查隐蔽工程记录。Testingmethod:Observeexaminationandcheckconcealedworkrecords
10.2一般项目GeneralItems
1)坐标和标高正确,排列整齐,标志桩和标志牌设置准确;防燃、隔热和防腐要求的电缆保护措施完整。Coordinateandelevationshouldbecorrectandarrangeneatly.Setupsignstakeandsignboardaccurately;takeprotectionflameproof,heatinsulationandcorrosionmatures.
2)电缆的埋置深度应符合下列要求:①电缆表面距地面的距离不应小于0.8m,且电缆应埋在冻土层以下。②在电缆引入建筑物、与地下建筑物交叉及绕过地下建筑物处等受条件限制时,可浅埋,但应采取保护措施。Thedepthofburiedcablesshouldmeetthefollowingrequirements:①Thedistancefromcablesurfacetogroundshouldbenotlessthan0.8m,andthecablesshouldbeburiedbelowthepermafrost.②Buryshallowlyifbeingrestrictedbytheconditiontopassthebuildingandbypassandcrossoverundergroundstructures,butshouldtakeprotectivemeasures.
3)直埋电缆铺砂盖板或砖时应防止不清除沟内杂物、不用细砂细土、盖板或砖不严,有遗漏部分,施工负责人应加强检查。Cleanupdebris,spreadfinesandandsoilsands,coverboardsorbrickstightlyandstrengtheninspectionsonmissingpart.
4)电缆进入室内电缆沟时,防止套管防水处理不好,沟内进水。应严格按规范和工艺要求施工。Whencablesarelaidinindoortrench,preventcasingforpoorwaterproofhandling.Workinstrictaccordancewithspecificationsandprocessrequirements.
5)有麻皮保护层的电缆进入室内,防止不作剥麻刷油防腐处理。Donotusestrippinghempbrushoilifbarkprotectivelayercablesarelaidindoor.
检验方法:观察检查和检查隐蔽工程记录及坐标图。Testingmethod:observeexaminationandcheckconcealedworksrecordsandcoordinatediagram.
十一.成品保护FinishedProtection
3)电缆两端头处的门窗装好,并加锁,防止电缆丢失或损毁。Installdoorsandwindowsandlockoncablebothends,topreventlossordamage.
十二.质量记录QualityRecord
12.1质量保证资料QualityAssuranceInformation
1)电缆产品合格证Cableproductcertification
2)电缆绝缘摇测记录或耐压试验记录Cableinsulationtestrollingorvoltagewithstandrecords
3)隐蔽工程验收记录Concealedprojectacceptance
12.2施工记录ConstructionofRecord
1)自互检记录。Selfandmutualinspectionrecords
DB35/T 1893-2020 生态环境大数据管理平台接口规范4)电缆走向实测图。Alignmentmeasuremap
十三.安全生产、文明施工要求和措施SafetyandCivilizedConstructionRequestsandMeasures
2)实行持证上岗操作制度,特殊工种操作人员必须持有特殊工种操作证,严禁无证操作,并及时做好登记。不断改善劳动条件,认真做好每个施工人员的劳动保护措施。Toimplementcertifiedoperatingsystem,specialtypesofworkmusthaveapermittooperate.Thosewithoutcertificatearenotallowedtoentersite,recordsmustbemade.Continuouslyimprovetheworkingconditionsandkeepthesafetymeasuresforeachworker.
3) 所有工作机具都经过业主验收合格后,贴上标签,方可使用。Allequipmentshouldbeinspected,acceptedbyownerandbelabeled.
4)电缆沟开挖直到回填土完工,应尽可能地均衡、连续施工,缩短工期;在有行人的场所内施工,电缆沟开挖后应有警示牌及维护。Constructinabalancedandcontinuouswaytoshortentheperiodbetweencabletrenchexcavationandbackfill;Thereshouldbewarningsignsandmaintenanceonpedestrianarea.
5)现场禁止吸烟HG/T 20638-2017标准下载,班前班中严禁饮酒。Nosmokingandalcoholduringworkingperiod.
6) 施工前做好技术交底和安全交底,对工人讲明工作中的安全注意事项,并做好JHA。DotechnicalandsecurityclarificationtotheworkersaboutsecurityprecautionsandmakeaJHA..
7) 总安全方案将遵循管理公司安全方案和业主的安全规定。Thesecurityplanshouldfollowthesafetyrequirements.