拆迁安置房工程高支模专项施工方案设计简图如下:
取1.0m单位宽度计算。计算简图如下:
W=bh2/6=1000×152/6=37500mm3,I=bh3/12=1000×153/12=281250mm4
DB11/T 1254-2015 再生水热泵系统工程技术规范 q=γ0(γGΣqGk+γQγLΣqQk)=1.1×[1.3×[0.3+(24+1.1)×0.95]×1.0+1.5×0.9×(1+2)×1.0]=38.982kN/m
q静=γ0γGΣqGk=1.1×1.3×[0.3+(24+1.1)×0.95]×1.0=34.527kN/m
q活=γ0γQγLΣqQk=1.1×1.5×0.9×(1+2)×1.0=4.455kN/m
q`=ΣqGk+ΣqQk=[0.3+(24+1.1)×0.95]×1.0+(1+2)×1.0=27.145kN/m
Mmax=0.1q静l2+0.117q活l2=0.1×34.527×0.22+0.117×4.455×0.22=0.159kN·m
σmax=Mmax/W=0.159×106/37500=4.239N/mm2≤[f]=15N/mm2
Qmax=0.6q静l+0.617q活l=0.6×34.527×0.2+0.617×4.455×0.2=4.693kN
τmax=3Qmax/(2bh)=3×4.693×103/(2×1000×15)=0.469N/mm2≤[τ]=1.4N/mm2
νmax=0.677q`l4/(100EI)=0.677×27.145×2004/(100×6000×281250)=0.174mm
νmax=0.174mm≤[ν]=min[L/250,5]=min[200/250,5]=0.8mm
计算简图如下:
q=γ0(γGΣqGk+γQγLΣqQk)=1.1×[1.3×[(0.3+(24+1.1)×0.95)×0.2+0.01]+1.5×0.9×(1+2)×0.2]=7.811kN/m
q静=γ0γGΣqGk=1.1×1.3×[(0.3+(24+1.1)×0.95)×0.2+0.01]=6.92kN/m
q活=γ0γGγLΣqQk=1.1×1.5×0.9×(1+2)×0.2=0.891kN/m
q`=ΣqGk+ΣqQk=[(0.3+(24+1.1)×0.95)×0.2+0.01]+(1+2)×0.2=5.439kN/m
Mmax=0.125q静l2+0.125q活l2=0.125×6.92×0.72+0.125×0.891×0.72=0.478kN·m
σmax=Mmax/W=0.478×106/67500=7.088N/mm2≤[f]=13N/mm2
Qmax=0.625q静l+0.625q活l=0.625×6.92×0.7+0.625×0.891×0.7=3.417kN
τmax=3Qmax/(2bh0)=3×3.417×1000/(2×50×90)=1.139N/mm2
τmax=1.139N/mm2≤[τ]=1.3N/mm2
νmax=0.521q`l4/(100EI)=0.521×5.439×7004/(100×9000×3037500)=0.249mm
νmax=0.249mm≤[ν]=min[L/250,5]=min[700/250,5]=2.8mm
4、支座反力计算
设计值Rmax=1.25ql=1.25×7.811×0.7=6.834kN
标准值R`max=1.25q`l=1.25×5.439×0.7=4.759kN
因可调托座内主楞根数为2,验算时取主楞受力不均匀系数=0.6。
计算简图1如下:
主楞弯矩图(kN·m)
主楞剪力图(kN)
主楞变形图(mm)
计算简图1支座反力设计值依次为R1=7.934kN,R2=15.646kN,R3=15.95kN,R4=5.684kN
计算简图1支座反力标准值依次为R'1=5.525kN,R'2=10.895kN,R'3=11.107kN,R'4=3.958kN
Mmax=1.021kN·m
Qmax=8.504kN
Vmax=0.962mm
计算简图2如下:
主楞弯矩图(kN·m)
主楞剪力图(kN)
主楞变形图(mm)
计算简图2支座反力设计值依次为R5=6.767kN,R6=15.84kN,R7=15.84kN,R8=6.767kN
计算简图2支座反力标准值依次为R'5=4.712kN,R'6=11.03kN,R'7=11.03kN,R'8=4.712kN
Mmax=1.016kN·m
Qmax=9.671kN
Vmax=0.946mm
σmax=Mmax/W=1.021×106/5080=200.888N/mm2≤[f]=205N/mm2
τmax=2Qmax/A=2×9.671×1000/489=39.555N/mm2
τmax=39.555N/mm2≤[τ]=125N/mm2
νmax=0.962mm≤[ν]=min[L/250,5]=min[700/250,5]=2.8mm
4、可调托座验算
最大支座反力设计值Rmax=max[R1,R2,R3,R4,R5,R6,R7,R8]/0.6=26.584kN
1.05×Rmax=1.05×26.584=27.913kN,27.913kN≤30kN
标准值R`max=max[R'1,R'2,R'3,R'4,R'5,R'6,R'7,R'8]/0.6=18.512kN
h/la=1500/700=2.143,h/lb=1500/700=2.143
l0=max[kμh,h+2a]=max[1.167×1.272×1500,1500+2×150]=2227mm
λ=l0/i=2227/15.9=141≤[λ]=210
长细比符合要求!
1) 模板支架风荷载标准值计算
μs=μst=0.172×1.2=0.206
ωk=μzμsω0=0.88×0.206×0.4=0.073kN/m2
2) 整体侧向力标准值计算
ωk=μzμsω0=0.88×1.3×0.4=0.458kN/m2
3、水平力引起的立杆附加轴力计算
水平力标准值:F=max[AFωkla/La,ΣGk×2%]=max[42.427×0.458×0.7/44.66,(24+1.1)×0.95×33.91×0.7×2%]=11.32kN
立杆附加轴力标准值:
立杆附加轴力设计值:N1=1.1×1.5×Nk=1.1×1.5×0.197=0.326kN
不组合风荷载时
Nut=γ0(γG∑NGk+1.5×0.9∑NQk)=Rmax+1.1×0.15γGH=26.584+1.1×0.15×1.3×3.6=27.356kN
σ=(1.05Nut+N1)/(φAKH)=(1.05×27.356+0.326)×103/(0.344×424×1)=199.166N/mm2≤[f]=205N/mm2
Nut=γ0(γG∑NGk+1.5×0.9∑NQk)=R'max+1.1×0.15γGH=26.584+1.1×0.15×1.3×3.6=27.356kN
Mw=γ0γQγLωk lah2/10=1.1×1.5×0.9×0.073×0.7×1.52/10=0.017kN·m
σ=(1.05Nut+N1)/(φAKH)+Mw/W=
(1.05×27.356+0.326)×103/(0.344×424×1)+0.017×106/(4.49×103)=202.943N/mm2≤[f]=205N/mm2
板模板(扣件式)计算书
设计简图如下:
取1.0m单位宽度计算。计算简图如下:
W=bh2/6=1000×152/6=37500mm3,I=bh3/12=1000×153/12=281250mm4
q=γ0(γGΣqGk+γQγLΣqQk)=1.1×[1.3×[0.3+(24+1.1)×0.65]×1.0+1.5×0.9×(1+2)×1.0]=28.214kN/m
q静=γ0γGΣqGk=1.1×1.3×[0.3+(24+1.1)×0.65]×1.0=23.759kN/m
q活=γ0γQγLΣqQk=1.1×1.5×0.9×(1+2)×1.0=4.455kN/m
q`=ΣqGk+ΣqQk=[0.3+(24+1.1)×0.65]×1.0+(1+2)×1.0=19.615kN/m
Mmax=0.1q静l2+0.117q活l2=0.1×23.759×0.22+0.117×4.455×0.22=0.116kN·m
σmax=Mmax/W=0.116×106/37500=3.09N/mm2≤[f]=15N/mm2
Qmax=0.6q静l+0.617q活l=0.6×23.759×0.2+0.617×4.455×0.2=3.401kN
τmax=3Qmax/(2bh)=3×3.401×103/(2×1000×15)=0.34N/mm2≤[τ]=1.4N/mm2
νmax=0.677q`l4/(100EI)=0.677×19.615×2004/(100×6000×281250)=0.126mm
νmax=0.126mm≤[ν]=min[L/250,5]=min[200/250,5]=0.8mm
计算简图如下:
q=γ0(γGΣqGk+γQγLΣqQk)=1.1×[1.3×[(0.3+(24+1.1)×0.65)×0.2+0.01]+1.5×0.9×(1+2)×0.2]=5.657kN/m
q静=γ0γGΣqGk=1.1×1.3×[(0.3+(24+1.1)×0.65)×0.2+0.01]=4.766kN/m
q活=γ0γGγLΣqQk=1.1×1.5×0.9×(1+2)×0.2=0.891kN/m
q`=ΣqGk+ΣqQk=[(0.3+(24+1.1)×0.65)×0.2+0.01]+(1+2)×0.2=3.933kN/m
Mmax=0.125q静l2+0.125q活l2=0.125×4.766×0.72+0.125×0.891×0.72=0.347kN·m
σmax=Mmax/W=0.347×106/67500=5.133N/mm2≤[f]=13N/mm2
Qmax=0.625q静l+0.625q活l=0.625×4.766×0.7+0.625×0.891×0.7=2.475kN
τmax=3Qmax/(2bh0)=3×2.475×1000/(2×50×90)=0.825N/mm2
τmax=0.825N/mm2≤[τ]=1.3N/mm2
νmax=0.521q`l4/(100EI)=0.521×3.933×7004/(100×9000×3037500)=0.18mm
νmax=0.18mm≤[ν]=min[L/250,5]=min[700/250,5]=2.8mm
4、支座反力计算
设计值Rmax=1.25ql=1.25×5.657×0.7=4.95kN
标准值R`max=1.25q`l=1.25×3.933×0.7=3.441kN
因可调托座内主楞根数为2,验算时取主楞受力不均匀系数=0.6。
计算简图如下:
主楞弯矩图(kN·m)
主楞剪力图(kN)
主楞变形图(mm)
计算简图支座反力设计值依次为R1=6.327kN,R2=13.037kN,R3=13.037kN,R4=6.327kN
计算简图支座反力标准值依次为R'1=4.4kN,R'2=9.068kN,R'3=9.068kN,R'4=4.4kN
σmax=Mmax/W=0.894×106/5080=176.013N/mm2≤[f]=205N/mm2
τmax=2Qmax/A=2×5.592×1000/489=22.872N/mm2
τmax=22.872N/mm2≤[τ]=125N/mm2
νmax=1.117mm≤[ν]=min[L/250,5]=min[800/250,5]=3.2mm
4、可调托座验算
最大支座反力设计值Rmax=max[R1,R2,R3,R4]/0.6=21.728kN
1.05×Rmax=1.05×21.728=22.814kN,22.814kN≤30kN
标准值R`max=max[R'1,R'2,R'3,R'4]/0.6=15.113kN
h/la=1400/700=2,h/lb=1400/800=1.75
l0=max[kμh,h+2a]=max[1.167×1.409×1400,1400+2×150]=2302mm
λ=l0/i=2302/15.9=145≤[λ]=210
长细比符合要求!
1) 模板支架风荷载标准值计算
μs=μst=0.177×1.2=0.212
ωk=μzμsω0=0.88×0.212×0.4=0.075kN/m2
2) 整体侧向力标准值计算
ωk=μzμsω0=0.88×1.3×0.4=0.458kN/m2
3、水平力引起的立杆附加轴力计算
水平力标准值:F=max[AFωkla/La,ΣGk×2%]=max[29.029×0.458×0.7/44.66,(24+1.1)×0.65×33.91×0.7×2%]=7.745kN
立杆附加轴力标准值:
立杆附加轴力设计值:N1=1.1×1.5×Nk=1.1×1.5×0.135=0.223kN
不组合风荷载时
Nut=γ0(γG∑NGk+1.5×0.9∑NQk)=Rmax+1.1×0.15γGH=21.728+1.1×0.15×1.3×3.6=22.5kN
σ=(1.05Nut+N1)/(φAKH)=(1.05×22.5+0.223)×103/(0.328×424×1)=171.481N/mm2≤[f]=205N/mm2
Nut=γ0(γG∑NGk+1.5×0.9∑NQk)=R'max+1.1×0.15γGH=21.728+1.1×0.15×1.3×3.6=22.5kN
Mw=γ0γQγLωk lah2/10=1.1×1.5×0.9×0.075×0.7×1.42/10=0.015kN·m
GB/T 39407-2020标准下载 σ=(1.05Nut+N1)/(φAKH)+Mw/W=
(1.05×22.5+0.223)×103/(0.328×424×1)+0.015×106/(4.49×103)=174.867N/mm2≤[f]=205N/mm2
附图1:高大模架施工范围图
附图2:施工流水段划分图
附图3:立杆平面布置图与剖面图
说明:支撑架立杆平面布置图(梁板要成一个体系,水平杆要拉通,含水平剪刀撑的布置形式、间距,竖向剪刀撑的布置位置、间距);支撑架剖面图(含下层或基础支撑情况、扫地杆、竖向剪刀撑的布置形式、间距,水平剪刀撑的布置位置、间距,与结构的拉接位置、自由端长度、安全网的位置、间距等)。
附图4:混凝土浇筑方向及浇筑顺序图(明确布料机的位置以及从中间向两边浇筑顺序)
附图5:施工监测点布置图(尽量布置在变形大且容易观测的位置,宜设在角部和四边的中间位置,每个区域内监测点数量不应小于3个)
Q-CR 9204-2015标准下载附图6:相关节点详图(梁支模节点图:包含梁两侧至少3跨板的支撑情况)(连墙件布置图应画出柱子四周的拉结做法)