T梁张拉计算及压浆施工方案△L = =1301.742*4.0883/(980*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1291.068*18.8682/980/1.96*105=12.69cm
L直2=P1×L/Ay×E=1312.416*3.83475/980/1.96*105=2.62cm
DB/T 29-121-2018标准下载 L=12.69+2.77*2+2.62*2=23.47cm
预应力筋截面面积Ay=140*6=980mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*980=1312.416KN
由图纸说明:θ=6.54°*3.14/180°=0.1141rad
L直1=7.1945*2=14.389m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*4.5661+0.1*0.1141
=1300.508KN
P×L
△L = =1300.508*4.5661/(980*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1288.599*14.389/980/1.96*105=9.66cm
L直2=P1×L/Ay×E=1312.416*5.61585/980/1.96*105=3.84cm
L=9.66+3.09*2+3.84*2=23.52cm
预应力筋截面面积Ay=140*6=980mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*980=1312.416KN
由图纸说明:θ=6.37°*3.14/180°=0.1111rad
L直1=5.2534*2=10.5068m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*4.4486+0.1*0.1111
=1300.814KN
P×L
△L = =1300.814*4.4486/(980*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1289.212*10.5068/980/1.96*105=7.05cm
L直2=P1×L/Ay×E=1312.416*7.68465/980/1.96*105=5.25cm
L=7.05+3.01*2+5.26*2=23.59cm
预应力筋截面面积Ay=140*6=980mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*980=1312.416KN
由图纸说明:θ=6.74°*3.14/180°=0.1176rad
L直1=3.1253*2=6.2506m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*4.7039+0.1*0.1176
=1300.148KN
P×L
△L = =1300.148*4.7039/(980*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1287.879*6.2506/980/1.96*105=4.19cm
L直2=P1×L/Ay×E=1312.416*9.5778/980/1.96*105=6.55cm
L=4.19+3.18*2+6.55*2=23.65cm
(二)35m T梁边主梁
预应力筋截面面积Ay=140*8=1120mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*1120=1499.904KN
由图纸说明:θ=2.23°*3.14/180°=0.0389rad
L直1=12.7011*2=25.4022m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*1.5577+0.1*0.0389
=1495.24KN
P×L
△L = =1495.24*1.5577/(1120*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1490.58*25.4022/1120/1.96*105=17.25cm
L直2=P1×L/Ay×E=1499.904*3.0739/1120/1.96*105=2.1cm
L=17.26+1.06*2+2.1*2=23.58cm
预应力筋截面面积Ay=140*8=1120mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*1120=1499.904KN
由图纸说明:θ=4.4°*3.14/180°=0.077rad
L直1=9.9438*2=19.8876m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*3.0709+0.1*0.077
=1490.731KN
P×L
△L = =1490.731*3.0709/(1120*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1481.558*19.8876/1120/1.96*105=13.43cm
L直2=P1×L/Ay×E=1499.904*4.33105/1120/1.96*105=2.96cm
L=13.42+2.09*2+2.96*2=23.52cm
预应力筋截面面积Ay=140*8=1120mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*1120=1499.904KN
由图纸说明:θ=5.46°*3.14/180°=0.0952rad
L直1=7.5735*2=15.147m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*3.8101+0.1*0.0952
=1488.533KN
P×L
△L = =1488.533*3.8101/(1120*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1477.161*15.147/1120/1.96*105=10.20cm
L直2=P1×L/Ay×E=1499.904*5.97925/1120/1.96*105=4.09cm
L=10.20+2.58*2+4.09*2=23.54cm
预应力筋截面面积Ay=140*8=1120mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*1120=1499.904KN
由图纸说明:θ=5.51°*3.14/180°=0.0961rad
L直1=5.5555*2=11.111m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*3.846+0.1*0.0961
=1488.428KN
P×L
△L = =1488.428*3.846/(1120*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1476.952*11.111/1120/1.96*105=7.47cm
L直2=P1×L/Ay×E=1499.904*7.97125/1120/1.96*105=5.45cm
L=7.47+2.61*2+5.45*2=23.59cm
预应力筋截面面积Ay=140*8=1120mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*1120=1499.904KN
由图纸说明:θ=6.02°*3.14/180°=0.105rad
L弯=4.2039m
L直1=3.3761*2=6.7522m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*4.2039+0.1*0.105
=1487.37KN
P×L
△L = =1487.37*4.2039/(1120*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1474.835*6.7522/1120/1.96*105=4.53cm
L直2=P1×L/Ay×E=1499.904*9.81185/1120/1.96*105=6.71cm
L=4.53+2.85*2+6.71*2=23.65cm
预应力筋截面面积Ay=140*8=1120mm2
锚下控制应力σk=0.72Ryb=0.72*1860=1339.2MPa
起始端头张拉力p1=σk*Ay=1339.2*1120=1499.904KN
由图纸说明:θ=6.39°*3.14/180°=0.111rad
L直1=1.2487*2=2.4974m
μ=0.1,R=0.0015,
P=P× =1124.928*
kL+μθ 0.0015*4.458+0.1*0.111
=1486.609KN
P×L
△L = =1486.609*4.458/(1120*1.96*105 )
Ay×Eg
L直1=P2×L/Ay×E=1473.313*2.4974/1120/1.96*105=1.68cm
L直2=P1×L/Ay×E=1499.904*11.70515/1120/1.96*105=8.00cm
L=1.68+3.02*2+8.00*2=23.72cm
千斤顶工作长度的伸长量计算:
ΔL=PL/AyEy=σk*Ay*L/AyEy=σk*L/Ey=1339.2*0.58/1.96*105
1、预应力筋张拉完毕后尽早压浆;
2、孔道压浆宜采用水泥浆,水泥浆强28天抗压强度不小于30Mpa (用70.7mm 立方体测试),水泥浆的技术条件应符合下列规定:
①、水泥宜采用硅酸盐水泥和普通水泥,水泥标号不得低于P.O 42.5;
②、水灰比宜为0.3~0.35,可掺入适量减水剂以增加流动性;
③、水泥浆的泌水率最大不得超过3%,拌和后3小时泌水率宜控制在2%,浆体流动度≤30S,泌水应在24h内重新全部被浆吸回;
④、流动性在流动性测定仪上进行试验,水泥浆自仪器内流出的时间不超过6秒;
⑤、膨胀率水泥浆中(通过试验)可掺入适当砼膨胀剂,膨胀剂的掺入量参照其与水泥用量的比例规定及试验所得结果,水泥浆掺入膨胀剂后的自由膨胀应小于10%;
⑥、收缩率不大于2%;
3、水泥浆的拌制,先下水再下水泥,拌和时间不得少于1minLY/T 3142-2019标准下载,灰浆过筛后存放在储浆桶内,水泥浆自调制到压入管道的时间间隔不得超过40分钟,水泥浆在灰浆桶仍不停地低速搅拌。
4、压浆前用高压水对孔道进行冲洗以排除孔内杂物,如有积水应用吹风排除,但要保持孔内润湿。
6、真空稳定后,保证真空泵运行的同时,往压浆端的水泥浆入口压浆。一条波纹管的压浆必须连续进行。
7、当透明胶管有水泥浆流出后,关闭真空阀,打开排浆阀继续压浆。压浆至浆体连续喷出且稠度与入浆体相当时,关闭排浆阀至压力为0.7Mpa左右,持压2分钟后关闭排浆阀。
8、持压过程中应从低到高依次打开埋设于波纹管各峰顶排气管,排出残余空气及泌水,保证浆体饱满。待浆体失去流动性后可拆除压浆阀及排气阀。
9、压浆过程中及压浆后48h内,结构砼的湿度不得低于5度,否则应采取保护措施,当气温高于35度时,压浆宜在夜间进行。
GBT 28799.2-2020 冷热水用耐热聚乙烯(PE-RT)管道系统 第2部分:管材.pdf10、孔道压浆时填好施工记录。