小区室外电缆沟施工方案碎石类土先用镐翻松,正向挖掘,每层深度,视翻土厚度而定,每层应清底和出土,然后逐步挖掘。Graveltypesoilfirstusepicktoloose,thenforwardexcavatewitheachlayerdepthdependedonthethicknessofdiggingsoil.Clearthebottomanddigouttheearthbylayerandthenexcavategradually.
5)在开挖槽边弃土时,应保证边坡和直立帮的稳定。当土质良好时,抛于槽边的土方(或材料),应距槽(沟)边缘0.8m以外,高度不宜超过1m。开挖基坑(槽)的土方,在场地有条件堆放时,留足回填需用的好土,多余的土方运出,避免二次搬运。Excavatesideearthshouldensurethestabilityoftheslopeandupright.Whenthesoilisfine,throwearthonthegrooveside(ormaterial)0.8mawayfromthepit(groove)edgewithheightmorethan1m.Stackbackfillsoilifithasconditionsandmovetheexcessearthouttoavoidsecondaryhandling.
机械与人工相结合开挖路线(A472至C581南线与北线)Mechanicalandmanualexcavationline(A472toC581SouthLineandNorthLine)
人工开挖路线(A472至B301S支线)Manualexcavationline(A472toB301SBranch)
在人工开挖路线上河道整治工程施工方案[1],安排人员进行开挖,不得机械开挖。开挖过程中需要小心谨慎,注意地下管线。Arrangepersonnelonmanualexcavationlineratherthantakingmechanicalexcavation.Payattentiontoundergroundpipelines.
雨期开挖基坑(槽)时,应注意边坡稳定,必要时可适当放缓边坡或设置支撑。同时应在坑(槽)外侧围以土堤或开挖水沟,防止地面水流入。施工时应加强对边坡、支撑、土堤等的检查。Onpluvialdaysexcavatepit(groove),payattentiontoslopestability.Ifnecessary,lowslopeorsetupsupport.Meanwhileencloseembankmentaroundthepit(groove)ordidaditchtopreventsurfacewaterinflow.Strengthenoncheckingtheslope,support,embankmentetc.
8)土方开挖不宜在冬期施工。如必须在冬期施工时,其施工方法应按冬施方案进行。Earthexcavationshouldnotbedoneinthewinterperiod.Ifnecessary,takewinterprogram.
开挖电缆沟时,必须防止沟底基土遭受冻结,如沟槽开挖完毕至埋设电缆之间,有较长的停歇时间,应在基底标高以上预留适当厚度的松土,或用其他保温材料覆盖Preventthegroovebasesoilbefrozen,suchastheintervalbetweentrenchexcavationandcablelayingreserveloosesoilwithappropriatethicknessabovebasementelevationorcoverwithotherthermalinsulationmaterial.
9)开槽后及时约请各有关人员验槽,验槽合格后方可进行下道工序。Inviterelatedpersonneltochecktheexcavatedtrenchandcarryoutthenextworkingprocedureafterpassingtheexamination.
六.质量控制QualityControl
6.1电缆沟外形尺寸允许偏差表Allowabledeviatedexternaldimensionsofcabletrenchtable
允许偏差项目allowabledeviation
电缆沟外形尺寸允许偏差allowabledeviatedexternaldimensionsofcabletrenchtable
允许偏差(mm)allowabledeviation
检验方法testmethod
标高elevation
+0mm ,-50mm
用水准仪检查waterlevelcheck
长度、宽度length,width
由设计中心向两边量、拉线和尺量检查designcentermeasureandpulllineonbothsidesandrulerinspection
steepsideslope
不允许notallowed
坡度尺检查gradientrulerinspection
6.2应注意的质量问题Qualityissues
4)施工顺序不合理:土方开挖宜先从低处开挖,分层分段依次进行,形成一定坡度,以利排水。Theconstructionsequenceisunreasonable:earthexcavationshouldbeginfromthelowerplace,layerbylayerandsectionbysectioninturn;formacertainslopetofacilitatedrainage.
5)开挖尺寸不足:电缆沟底部的开挖宽度,应根据施工需要增加工作面宽度。Theexcavationsizeisnotenough:Cabletrenchbottomwidthshouldbeincreasedasperconstructionneeds.
6)电缆沟边坡不直不平、基底不平:应加强检查,随挖随修,并要认真验收。Slopeisnotstraightandbaseisuneven:strengtheninspection,repaircabletrench,andthenacceptseriously.
七.成品保护FinishedProtection
2)土方开挖时,应防止邻近已有建筑物或构筑物、道路、管线等发生下沉和变形。必要时应与设计单位或建设单位协商采取防护措施,并在施工中进行沉降或位移观测。Notesubsidenceanddeformationofneighboringexistingbuildingsorstructures,roads,pipelinesetc.Takeprotectivemeasureswithdesignandconstructionunitandconstructobservationonsettlementordisplacement.
3)在敷设有地上或地下管线、电缆的地段进行土方施工时,应事先取得有关管理部门的书面同意,施工中应采取措施,以防止损坏管线,造成严重事故Conductearthworkontheareaneedstolaygroundorundergroundpipelines,cablespriortogettingwrittenconsentoftherelevantadministrativedepartments.Onconstructiontakemeasurestopreventdamagingpipelinesandcauseseriousaccidents.
八.施工记录ConstructionofRecord
1)自互检记录。Selfandmutualinspectionrecords
九.安全生产、文明施工要求和措施SafetyandCivilizedConstructionRequestsandMeasures
1)开工前应做好施工场地内的道路,开辟适当的工作面,做好检查和必要的加宽、加固工作XX 区行政商业中心室内给排水、消防及自动报警系统施工组织设计,以利安全施工。Buildsiteroadsandappropriateworkarea.Widenandstrengthenordertofacilitatesafeconstruction.
2)电缆沟开挖工程应注意边坡和基坑的稳定性,一般应按先深后浅的顺序施工,并应采取必要的保护措施。Notethestabilityoftheslopeandbase,generallyconstructfromdeeptoshallowandtakenecessaryprotectivemeasures.
4)夜间施工时,应合理安排施工项目,防止挖方超挖超深。施工现场应根据需要设置足够的照明设施,在危险地段应设置红灯警示。Rationallyarrangenightconstructionprojectsandpreventtheultraexcavation.Theconstructionsetupadequatelightingfacilitiesandredlightwarningondangerouslines.
5)土方开挖前,应会同有关单位对附近以有的建筑物、构筑物、道路等管线进行检查和鉴定,并在整个施工期间,加强监测,发现问题应与设计或建设单位协商采取防护措施,并及时处理。Inspectandappraisenearbybuildings,structures,roads,pipelineswithrelevantunits.Strengthenmonitoringandconsultwiththedesignortheconstructionunittotakeprotectivemeasuresandtimelyprocessissuesfound.
6)电缆沟四周设置的防护栏杆应符合安全规定。Aroundcabletrenchsetprotectiverailingsaspersafetyrequirements.
8)电缆沟的开挖或回填应连续进行,尽快完成。施工中应防止地面水流入沟内,以免边坡塌方或基土遭到破坏。Cabletrenchexcavationorbackfillingshallbecontinuousandspeedy.Preventwatergoingintothetrenchtocauseslopeordamagethebase.
9)雨季施工或电缆沟挖好后不能及时进行下一道工序时,可在基底标高以上留150~300MM一层不挖,待下一工序开始时再挖除。Donotdothenextprocesswhenfinishtheexcavationoronrainingseason,butleave150~300MMbaseelevationuntilthenextprocess.
10)开工前准备好安全设施,现场安排充足的管理人员,做到随时有人巡检;机械作业必须有人守护,防止事故发生;进场的工人必须进行安全教育培训,挖土前必须进行技术交底并签字,同时与工人签定安全用工合同。Preparesafetyfacilitiesandadequatemanagementpersonneltodosomeinspectionatanytime;machineoperationsmustbeguardedtopreventaccidents;conductsafetyeducationandtrainingandtechnicalclarification;signsafetyemploymentcontractswithworkers.
HJ 347.2-2018 水质 粪大肠菌群的测定 多管发酵法附厂区电缆沟图:Attached:cabletrenchdrawing