施工组织设计下载简介
内容预览随机截取了部分,仅供参考,下载文档齐全完整
“鸟巢”施工组织设计冲切系数α=0.27/(λ+0.2)=0.27/(0.57+0.2)=0.94
抗冲切力4α(b+a)fLho=4×0.94(2000+600)1.1×1050=11291KN
GB/T 37755-2019标准下载4294<11291安全
NLQmax-G/4=1261-750/4=1074KN
λ=0.57α=0.48/(λ+0.2)=0.48/(0.57+0.2)=0.62
L=2C-0.2d+0.8a=2×0.9-0.2×0.6+0.8×0.6=2.16m
代入αLfCho=0.62×2160×1.1×1050=1547KN
1074<1547安全
V=2(Qmax-G/4)=2(1261-750/2)=1772KN
λ=0.57β=0.12/(λ+0.3)=0.12/(0.57+0.3)=0.14
代入βfcho=0.14×9.6×5000×1050=7056KN
1772<7056安全
Mx=My=2Qmin(a+b/2)=2×538×0.9=968KN.m
Ag=Mx/0.9hofg=968×106/0.9×1050×210=4880mm2
Rb=Kf(Mf-Mp)/2A,=1.4(4834-2746)/2×3.8=384KN
Rb<Qmin=538,勿需在算。
假定qpk=1000KN/m2qsik=40KN/m2
Ap=(1/4)η0.62=0.28m2
U=π0.6=1.89m
单桩承受最大荷载Qmax=1261KN
L=(Ra-gpkAP)/Uqsik
L=(1261-1000×0.28)/1.89×40=13m
R1=φ(fcAP+f,yA,s)=9.6N/mm2×0.28×10002+f,yA,s
=2688KN+f,yA,s>Ra=1261KN
受拉桩Qmin=538
1.2Qmin=1.2×538=646<Rb=1073安全
As=Rb/fy=646×103/300=2153
选φ20需n=2153/314=7根
同上荷载,改变承台尺寸为3.2*3.2*1.2m
N=695KNM=4647KN.mH=156.2KN
N+G=695+3.2×3.2×1.2×25=695+307=1002KN
M=4647+156.2×1.2=4834KN.m
Mx=0.707M=0.707×4834=3418KN.m
Qmaxmin=(N+G)/4±Mx/2yi=1002/4±3418/2=250±1709=1959KN
或根据荷载表(见塔吊说明书)
Q压=191.6T+30.7/4=199.2T=1992KN
Q拉=156.9T-30.7/4=149T=1490KN
由于予埋节直接作用于桩上,勿需计算承台冲切与配筋
Mf=4834KN.m
Mp=(N+G)A,/2=1002×1=1002KN.m
需桩承担(两根中的一根)
单桩应具有抗压1959KN的能力,同时还应具有抗拉1.2×1459KN=1750KN的能力。它既满足作用力的要求也满足抗倾覆的要求。
Qpk=1000KN/m2qsik=40KN/m2
A=0.25π×0.72=0.385m2u=0.7π=2.2m
L=(Ra-qpkAp)/Uqsik=1959-1000×0.385/2.2×40=18m
Rb=γApL+UqsikL
DB3202T 1001-2018 无锡市智能制造水平评价规范.pdfL=Rb/(γAp+Uqsik)=1750/25×0.385+2.2×40=18m
As=Rs/fy=1750×103/300=5833mm2
n=5833/314=19根
20×40=800mm
调整承台尺寸为3.4×3.4×1.2m
5×5×1.2=30m3
3.4×3.4×1.2=13.82m3
新疆某高级中学运动场改造工程施工组织设计方案32+32+17+17根/1.18T