海萨2x600MW锅炉主要施工方案

Hisar2×600MW Boiler Main Erection Plan

JC/T 418-2009 用于水泥中的粒化高炉钛矿渣.pdf本期建设规模2×600MW燃煤发电机组。锅炉由SEC提供。锅炉为亚临界参数、强制循环、一次中间再热、单炉膛平衡通风、固态排渣、露天布置、全钢构架的∏型汽包炉。 This project is 2×600MW coal fired thermal units, boiler shall be supplied by SEC. The boiler is all steel structural ∏ type drum boiler of a subcritical parameter, pump circulation, single reheat, single furnace balance draft, dry slagging and hypaethral placement.

锅炉施工方案 Boiler Erection Plan

锅炉为上海电气集团生产的亚临界参数、强制循环、一次中间再热、单炉膛平衡通风、固态排渣、露天布置、全钢构架的∏型汽包炉。

The Boiler shall be supplied by SEC. The boiler is all steel structural ∏ type drum boiler of a subcritical parameter, pump circulation, single reheat, single furnace balance draft, dry slagging and hypaethral placement.

1 施工场地及主吊机械 Erection site and main hoisting equipments

1.1 施工场地布置 Erection site plot

锅炉组合场布置按总平面布置图,组合场内布置50t龙门吊各4台,锅炉受热面的大部分组合工作安排在此完成。

Boiler assembly yard will be arranged as per general layout drawing. Four 50T gantry cranes will be provided respectively. Assembly of most heating surface structures will be done in this area.

1.2 施工机械选择 Selection of construction plants

(1) FZQ2010/ 80T圆筒吊 FZQ2010/ 80T cylindrical crane

(2) 250t履带吊 250t Crawler crane

CC1400/250t履带吊为锅炉主吊机械,采用SWSL塔式工况,后配重40t,主臂角度85度:主副臂:72m加36m;最大作业半径42m,负荷27t;最小作业半径24m时,负荷为39t。 CC1400/250 Crawler cranes are designed as main boiler hoisting euqipment, adopting SWSL tower working conditions, with a banlance weight of 40t and main jib angle of 85°; length of main & auxiliary jib,72+36m, max working radius 42m,load 27t;min working radius 24m,load 39t.

吊装主要内容为:Main hoisting scope:

a. 锅炉钢架吊装。Boiler steel structure lifting.

b. 锅炉受热面吊装、空气预热器吊装。Boiler heating surface ,airpreheater lifting.

c.烟、风、煤管道安装 Flue gas,air,coal piping erection.

d. 根据现场实际换工况用于大件设备的安装和卸车工作。 Employed in erection of other heavy equipments and unloading works.

CC1400/250t履带吊性能表(SWSL塔式、后配重40t工况)主附臂(主臂角度85º):72m+36m。CC1400/250t crawler crane performance list(SWSL TOWER type,banlance weight 40t), main & auxiliary jib,72+36m(main jib angle of 85°) .

(4) 其它吊装机械 Other lifting plants

A四台50t龙门吊布置于锅炉组合场,负责设备装卸车、受热面膜式壁及蛇行管排的组合工作及烟风道的制作组合工作。 4 frame cranes of 50t shall be arranged in Boiler structure assembly yard, employed in equipments loading and unloading, heating surface and pipe coil assembly works and flue/air ducting fabricating asembly works.

b. 50t汽车吊负责现场设备卸车倒运等工作。 .

b. Truck crane of 50t shall be employed in equipments unloading in site.

c.卷扬机布置在锅炉0m,辅助进行炉膛内管排及小件的吊装。 c . winch shall be arranged in 0m, assisting furnace internals lifting and the lifting of some samll units.

(5) 施工电梯布置 service lift arrangment

为方便锅炉施工,在炉一侧布置一施工电梯。Sservice lifts shall be arranged in each side of the boiler.

地铁科学馆站路灯拆迁施工组织设计方案2锅炉本体钢架安装 Boiler steel structure erection

钢架内侧柱为主要承重钢柱,外侧副柱则通过梁、水平支撑与内侧柱相连,以增加钢架的整体稳定性。钢结构从前至后共有6排。锅炉钢架的连接,采用高强螺栓和焊接相结合的方式,顶板和主梁与次梁之间,柱和梁之间,垂直支撑、水平支撑之间采用扭剪型高强螺栓连接,其余构件间采用焊接连接。 Internal pillars of the structure are designed for bearing, while the external pillars are designed to reinforce the entire stability of structure by connecting with girders, lateral supporting and internal pillars. There are 6 rows. Bolt and welding are employed in the connection of structure.

2.1 吊装方案 Hoisting plans

2.2 施工顺序 Construction procedure

锅炉基础划线→标高复验和基础凿毛→柱底板安装→立柱1m标高线复检→结构第一段吊装→整体找正→柱脚二次浇灌→其它几层结构吊装→顶板梁吊装→钢结构完善。

Boiler Foudation Lining→ Level Call Back And Surface Preparation →Column Plate Erection →Column 1m Level Callback →Structure Erection Stage 1→ Structure Alignment → Column Foot Secondary Grouting →Other Floors Lifting →Roof Plate Girder Lifting →Stucture Maintenance

Q/GDW 1868-2012 风电场接入系统设计内容深度规定.pdf3顶板梁吊装方案 Roof girder hoisting plans

锅炉钢结构第八段立柱、横梁、拉条安装完毕后,根据大板梁吊装需要,部分杆件预留,经检验合格,才能进行板梁吊装。

锅炉顶板梁的吊装机械为FZQ2010/80t圆筒吊和CC1400/CC2500履带吊。FZQ2010/80t圆筒吊布置在#1、#2炉的两侧,每台炉有一台磨机缓装,CC2500/CC1400履带吊在2台炉中间机动布置,看情况缓装一台磨煤机,使CC2500/CC1400满足顶板梁吊装工况。。 FZQ2010/80t cylindrical crane and CC1400/CC2500 crawler crane are employed to hoist boiler roof plate girder. FZQ2010/80t cylindrical crane should be arranged in both sides of boiler #1and#2, each boiler should be arranged with one mill after later. , while CC1400 or CC2500 crawler crane should be arranged between the tow boilers ,one mill should be erected later if necessary so that CC2500/CC1400 can meet the requirement of roof plate girder hoisting.