轻型井点降水方案.doc

轻型井点降水方案.doc
仅供个人学习
反馈
标准编号:
文件类型:doc
资源大小:0.2 M
标准类别:建筑工业标准
资源ID:390445
下载资源

标准规范下载简介

轻型井点降水方案.doc

一、工程概况···································································2

二、编制依据····································································2

三、降水方案选择·······························································2

某工业园宿舍楼F栋大施工组织设计编制四、井点降水相关计算·························································3

五、主要降水设备·······························································6

六、施工工期·····································································7

七、井点施工方法·······························································7

八、质量标准及质量保证措施················································*

*、危险点分析································································10

十、安全生产及文明施工措施···············································10

十一、环保措施································································11

本期设计为2×600MW亚临界汽轮发电机组。

工程地质情况:本工程持力层采用③圆砾层做持力层,③圆砾,层顶一般埋深3.0m~4.5m,一般厚度6.5m~9.5m。④细中砂层,层顶埋深一般为10.0m~13.0m。一般厚度5.0m~7.0m。⑤圆砾层分布于④层之下。层顶一般埋深15.0m~1*.0m。⑥粘土(残积土),褐色,稍湿,坚硬,覆于凝灰岩之上。最大厚度大于6.*m。

《火电施工质量检验及评定标准》

《电力建设施工及验收技术规范》

H≥H1+h+iL+l

式中H——井点管的埋设深度(m)

H1——井点埋设面至基坑底面距离(m)取3.0m

h——基坑中央最深挖掘面至降水曲线点的安全距离(m)取1.0m

L——井点管中心至基坑中心的短边距离(m)取27

i——降水曲线坡度取1/10

l——滤管长度(m)取1.2

H≥3.0+1.0+27×1/10+1.2=7.9m取*m

Q——井点系统总涌水量(m3/d)

K——渗透系数(m/d)取150

H——含水层厚度(m)计算暂取11m

R——抽水影响半径(m)计算取91

S——水位降低值(m)取1.2,地下水位取6.*m

XO——基坑设想半径(m)计算取24

本工程以无压非完整井计算

Q=1.366×150

3、计算井点管数量和间距

单井出水量q=65πdl×3K

=65×3.14×0.05×1.2×3150

n=1.1Q/q=149根

基坑四角处及机械入口处井点管应加密,则采用的井点管数量为149+32=1*1根

布置时,为使机械挖土有开行路线,宜布置成端部开口(即留6根井点管距离),因此实际需要井点管数量为:

4、校核水位降低数值:

此值与需要降低水位数值1.2m相符,故布置可行。

2、射流泵轻型井点降水井点为167根,总管(其中导流总管120m)长度为320m,配用循环水箱(1200×1200×1500×4mm)2个。

5、排水管长度按现场集水箱到下水道的实际距离定,管径至少选用φ100以上。

井点降水开工时间为2005年4月20日时代大厦工程施工组织设计,2005年4月30日达到降水效果进行基础土方二次开挖施工。

布置井点管井点管与总管连接试抽水进入工作状态基础结束及回填完后拔管。

2)、井点管埋设完毕,应接通总管与抽水设备进行试抽水。检查有无漏水,漏气现象,出水是否正常,有无淤塞现象,如有异常情况应及时进行修理。

井点管工作后,应保证连续不断的排水,正常出水规律是“先大后小,先混后清”。如不上水,或水一直较混或出现清后水混等情况,应立即检查纠正。

待地下构筑物竣工并进行回填土后,方可拆除井点系统,所留孔洞用砂或土填塞。

降水设施完毕后开始降水,降水对在汽轮机基础底板四角及中部钻设直径为400mm水位观测孔5个(深2.0m),观测孔设置于无设备基础的空白位置,降水过程中随时观测水位并进行记录,发现水位异常随时汇报。降水过程中水泵设备设专职人员昼夜进行值班,观测各井点降水情况和各泵运行情况,如下渗水量不满足水泵运行时,及时更换水泵。水位降至设计基层下0.5m后,进行土方施工。