低层建筑脚手架施工方案R<6.40kN,thedesigncalculationofsinglefastenerskidresistancecapabilitymeettherequirement.
10.5脚手架荷载标准值:
昆山某钻孔灌注桩工程施工组织设计-secret10.5Standardvalueofscaffoldload:
作用于脚手架的荷载包括静荷载、活荷载和风荷载。静荷载标准值包括以下内容:
Thestandardvalueofthescaffoldloadincludesstaticload,liveloadandwindload.Thecharacteristicvalueofstaticloadincludesthefollowingcontents:
每米立杆承受的结构自重标准值(kN/m);本例为0.1248
Theselfweightstandardvalueofthepilepermeter(kN/m);inthisprojectis0.1248
NG1=0.125×10.500=1.310kN;
脚手板的自重标准值(kN/m2);本例采用木脚手板,标准值为0.35
Theselfweightstandardvalueofthescaffold(kN/m2);thisprojecttakeswoodenscaffold,thestandardvalueis0.35
NG2=0.350×3×1.500×(1.050+0.3)/2=1.063kN;
栏杆与挡脚手板自重标准值(kN/m);本例采用栏杆木,标准值为0.14。
Standard dead weight of railing and scaffolding baffle (KN/m);railing wood is adopted in this project and its standard value is 0.14.
NG3=0.140×3×1.500/2=0.315kN;
吊挂的安全设施荷载(kN/m2);0.005
NG4=0.005×1.500×10.500=0.079kN;
经计算得到,静荷载标准值
Aftercalculating,thestaticloadstandardvalue:
NG=NG1+NG2+NG3+NG4=2.767kN;
活荷载为施工荷载标准值产生的轴向力总和,内、外立杆按一纵距内施工荷载总和的1/2取值。
Theliveloadisthetotalamountoftheaxialforcewhichisgeneratedbytheconstructionloadstandardvalue,theinternalandexternalpilestake1/2ofthetotalamount.
经计算得到,活荷载标准值
Aftercalculating,theliveloadstandardvalue:
NQ=2.000×1.050×1.500×2/2=3.150kN;
风荷载标准值应按照以下公式计算
Thestandardvalueofthewindloadshouldbecalculatedasthefollowingformula:
Wo=0.350kN/m2;
经计算得到,风荷载标准值
Aftercalculating,thewindloadstandardvalue:
Wk=0.7×0.350×0.615×1.200=0.181kN/m2;
不考虑风荷载时,立杆的轴向压力设计值计算公式
N=1.2NG+1.4NQ=1.2×2.767+1.4×3.150=7.731kN;
考虑风荷载时,立杆的轴向压力设计值计算公式
N=1.2NG+0.85×1.4NQ=1.2×2.767+0.85×1.4×3.150=7.069kN;
风荷载设计值产生的立杆段弯矩MW计算公式
Theformulaoftheuprightstanchionbendingsectionthatgeneratedbythewindloaddesignedvalueis:
Mw=0.85×1.4WkLah2/10=0.850×1.4×0.181×1.500×1.8002/10=0.105kN.m;
10.6立杆的稳定性计算:
10.6Thecalculationoftheuprightstanchionstability:
不组合风荷载时,立杆的稳定性计算公式为:
Whenthewindloadisnotconsidered,theformulaoftheuprightstanchionstabilityis:
立杆的轴心压力设计值:N=7.731kN;
计算立杆的截面回转半径:i=1.58cm;
Thecalculationofthesectionalradiusofgyrationoftheuprightstanchion:i=1.58cm;
计算长度附加系数:K=1.155;
Thecalculationofthelengthadditionalfactor:K=1.155;
计算长度系数参照《扣件式规范》表5.3.3得:U=1.500
Thecalculationofthelength,seeFastenerspecifications,table5.3.3,U=1.500
计算长度,由公式lo=kuh=kuh确定:lo=3.119m;
Thecalculationofthelengthislo=3.119m;basedontheformulalo=kuh
Lo/i=197.000;
轴心受压立杆的稳定系数φ,由长细比lo/i的结果查表得到:φ=0.186;
立杆净截面面积:A=4.89cm2;
立杆净截面模量(抵抗矩):W=5.08cm3;
钢管立杆抗压强度设计值:[f]=205.000N/mm2;
σ=7731.000/(0.186×489.000)=84.996N/mm2;
立杆稳定性计算σ=84.996小于[f]=205.000N/mm2满足要求!
Thecalculationoftheuprightstanchionstabilityσ=84.996,lessthan [f]=205.000N/mm2cansatisfytherequirements.
考虑风荷载时,立杆的稳定性计算公式
Whenthewindloadisconsidered,theformulaoftheuprightstanchionstabilityis:
立杆的轴心压力设计值:N=7.069kN;
计算立杆的截面回转半径:i=1.58cm;
Thecalculationofthesectionalradiusofgyrationoftheuprightstanchion:i=1.58cm;
计算长度附加系数:K=1.155;
Thecalculationofthelengthadditionalfactor:K=1.155;
计算长度系数参照《扣件式规范》表5.3.3得:U=1.500
Thecalculationofthelength,seeFastenerspecifications,table5.3.3,U=1.500
计算长度,由公式lo=kuh确定:lo=3.119m;
Thecalculationofthelengthislo=3.119m;basedontheformulalo=KUh
lo/i=197.000;
轴心受压立杆的稳定系数φ,由长细比lo/i的结果查表得到:φ=0.186
立杆净截面面积:A=4.89cm2;
立杆净截面模量(抵抗矩):W=5.08cm3;
钢管立杆抗压强度设计值:[f]=205.000N/mm2;
σ=7069.230/(0.186×489.000)+104569.655/5080.000=98.308N/mm2;
立杆稳定性计算σ=98.308小于[f]=205.000N/mm2满足要求!
Thecalculationoftheuprightstanchionstabilityσ=98.308,lessthan [f]=205.000N/mm2cansatisfytherequirements.
10.7最大搭设高度的计算:
10.7Thecalculationofthemaximumsetupheight:
不考虑风荷载时,采用单立管的敞开式、全封闭和半封闭的脚手架可搭设高度按照下式计算:
构配件自重标准值产生的轴向力NG2K(kN)计算公式为:
NG2K=NG2+NG3+NG4=1.457kN;
活荷载标准值:NQ=3.150kN;
Thestandardvalueoftheliveload:NQ=3.150kN;
每米立杆承受的结构自重标准值:Gk=0.125kN/m;
Theselfweightstandardvalueoftheuprightstanchionpermeter:Gk=0.125kN/m;
脚手架搭设高度Hs等于或大于26米,按照下式调整且不超过50米:
ThesetupheightofthescaffoldHsisequalorhigherthan26m,theadjustmentshouldnotbegreaterthan50m:
[H]=83.382/(1+0.001×83.382)=76.965m;
[H]=76.965和50比较取较小值。得到,脚手架搭设高度限值[H]=50.000m。
Takethelowervaluebetweenthe[H]=76.965and50,thengetthesetupheightofthescaffold[H]=50.000m.
考虑风荷载时,采用单立管的敞开式、全封闭和半封闭的脚手架可搭设高度按照下式计算:
构配件自重标准值产生的轴向力NG2K(kN)计算公式为:
NG2K=NG2+NG3+NG4=1.457kN;
活荷载标准值:NQ=3.150kN;
NQ–Thestandardvalueoftheliveload:NQ=3.150kN;
每米立杆承受的结构自重标准值:Gk=0.125kN/m;
计算立杆段由风荷载标准值产生的弯矩:Mwk=Mw/(1.4×0.85)=0.105/(1.4×0.85)=0.088kN.m;
Mwk–thecalculationoftheuprightstanchionbendingsectionthatgeneratedbythewindloaddesignedvalue:MMwk=Mw/(1.4×0.85)=0.105/(1.4×0.85)=0.088kN.m;
脚手架搭设高度Hs等于或大于26米,按照下式调整且不超过50米:
ThesetupheightofthescaffoldHsisequalorhigherthan26m,theadjustmentshouldnotbegreaterthan50m:
[H]=75.298/(1+0.001×75.298)=70.025;
[H]=70.025和50比较取较小值。经计算得到,脚手架搭设高度限值[H]=50.00m。
Takethelowervaluebetweenthe[H]=70.025and50,thengetthesetupheightofthescaffold[H]=50.00m.
10.8连墙件的计算:
10.8Thecalculationofthewallpieces:
连墙件的轴向力计算值应按照下式计算:
风荷载基本风压值Wk=0.181kN/m2;
ThefundamentalwindpressurevalueofthewindloadWk=0.181kN/m2;
每个连墙件的覆盖面积内脚手架外侧的迎风面积Aw=16.200m2;
ThewindwardareaoftheexternalsideofscaffoldineverywallpieceAw=16.200m2;
连墙件约束脚手架平面外变形所产生的轴向力(kN),No=5.000kN;
风荷载产生的连墙件轴向力设计值(kN),应按照下式计算:
NLw=1.4×Wk×Aw=4.101kN;
连墙件的轴向力计算值NL=NLw+No=9.101kN;
由长细比l/i=300.000/15.800的结果查表得到0.949;
Gettheresultof0.949basedontheratioofslendernessl/i=300.000/15.900
A=4.89cm2;[f]=205.00N/mm2;
Nl=9.101
Nl=9.101
连墙件采用双扣件与墙体连接。
Thewallpiecestakethedoublefastenertoconnectwiththewallbody.
经过计算得到Nl=9.101小于双扣件的抗滑力16.0kN,满足要求!
Aftercalculating,Nl=9.101islessthantheskidresistance16.0kNofthedoublefasteners,itsatisfiestherequirements.
10.9立杆的地基承载力计算:
10.9Thecalculationofthegroundbearingcapacityoftheuprightstanchion:
立杆基础底面的平均压力应满足下式的要求
Theaveragepressureofthefoundationbedoftheuprightstanchionshouldsatisfythefollowingformula:
Thegroundbearingcapacitydesignedvalueis:
fg=fgk×Kc=110.000kN/m2;
其中,地基承载力标准值:fgk=220.000kN/m2;
Thestandardvalueofthegroundbearingcapacityis:fgk=220.000kN/m2;
脚手架地基承载力调整系数:kc=0.500;
Thevariationvalueofthegroundbearingcapacityofthescaffoldis:kc=0.500;
立杆基础底面的平均压力,p=N/A=78.547kN/m2;
Theaveragepressureofthefundamentalgroundingoftheuprightstanchion,p=N/A=78.547kN/m2;
其中,上部结构传至基础顶面的轴向力设计值:N=7.069kN;
基础底面面积(m2):A=0.090m2。
Thefundamentalgroundingarea (m2):A=0.090m2.
p=78.547≤fg=110.000kN/m2。
地基承载力的计算满足要求!
Thecalculationofthegroundbearingcapacitysatisfiestherequirements.
11附图(平面、立面)
11AttachedFigures(plane&elevation)
12QualityControl
13ConstructionProcess
14EmergencyManagement
应急小组:EmergencyGroup
组长/Leader:陈肯/ChenKen
副组长/ViceLeader:陈兴明/ChenXingMing
成员/Members:杜小均/DuXiaoJun张成林/ZhangChengLin忠诚/ZhongCheng
周永川/ZhouYongChuan
EmergencyGroupLeader
13608363637
ChenXingMing
13527542237
13399872611
ZhangChengLin
GB/T 40134-2021 航天系统电磁兼容性要求.pdf18281835139
ZhouYongChuan
15823874958
EmergencyServices
SY/T 4212-2017标准下载Nanbahospital
XIABahospital
NanbaSafetyControllingCenter